Project Overview
This will be a passive park in north Auburn located on Shelton Mill Road between East University Drive and US 280. The project will include trails, a pavilion and restrooms, a play area and parking.
Please note that project completion dates are subject to change based on weather and other conditions. Project anticipated finish dates may not coincide with actual day of opening.
Opening: An official facility opening date for the public will be coordinated by the contractor and City staff, and will be announced at a later date.
Status
- Design
- Bid Advertisement
- Contracts
- Construction
35%
The contractor continues to work on installing utilities for the site and the widening of Shelton Mill Road for turn lanes to the park.
Photos




Timeline
Close Out Finishes
Jun 11, 2025
Close Out Starts
May 13, 2025
Construction Finishes
May 12, 2025
Construction Starts
Sep 30, 2024
Contracts Finishes
Sep 13, 2024
Contracts Starts
Aug 15, 2024
City Council / AWWB Starts
Aug 6, 2024
Bid Opening Starts
Jul 23, 2024
Bid Advertisement Finishes
Jul 19, 2024
Bid Advertisement Starts
Jun 30, 2024
Design Finishes
May 31, 2024
Design Starts
Apr 12, 2024